Beranda

Jumlah OPD 48 Selengkapnya
Jumlah Sub Kegiatan 42/ 1,660 Selengkapnya
Jumlah Paket 0/ 2,353 Selengkapnya
Jumlah Konstruksi 0/ 5 Selengkapnya

Laporan Rekapitulasi Bulanan

1 Januari 2025 sampai dengan 22 Juli 2025

Pekerjaan

Sub Kegiatan Selesai 0% 0/42
Paket Selesai 0% 0/0
Konstruksi Selesai 0% 0/0

Struktur Anggaran (BPKAD)

BELANJA
Rp15.531.147.685,00 / 95%
Pegawai
Rp1.013.960.000,00 / 88%
Non Pegawai
Rp14.517.187.685,00 / 95%
Barang/Jasa
Rp8.135.313.940,00 / 93%
Modal
Rp6.381.873.745,00 / 98%

Struktur Sub Kegiatan (BPKAD)

  • Jumlah 42
  • Selesai 0
  • Tidak Selesai 0
  • Berjalan 0
  • Belum Berjalan 42

Struktur Sumber Anggaran (BPKAD)

  • APBD
    Rp701.102.355.756,00 / 3.191%

Laporan Bulanan Fisik (BPKAD)

Laporan Bulanan Keuangan (BPKAD)

Rangking Pelaporan OPD

Total 48 hasil
#OPDPagu AnggaranPagu SerapanNilai KontrakRealisasi Progres LaporanJumlah Sub Kegiatan#####Realisasi Laporan Bulan
1DISDUKCAPILRp20.582.687.800,00Rp10.305.754.765,00Rp0,0050%2626001214Bulan 7
2DLHRp35.193.241.220,00Rp16.903.059.535,00Rp0,0048%5454004410Bulan 7
3DINKESRp403.990.950.528,00Rp138.464.901.891,00Rp0,0034%7272003834Bulan 7
4SETWANRp116.443.176.326,00Rp37.987.437.624,00Rp0,0033%5858003820Bulan 7
5DISKOMINFOSATIKRp20.088.732.108,00Rp5.981.983.809,00Rp0,0030%4545002916Bulan 7
6INSPEKTORATRp25.338.452.326,00Rp12.395.509.334,00Rp0,0049%3434002113Bulan 6
7DKPPRp33.211.811.573,00Rp11.881.444.931,00Rp0,0036%4747002522Bulan 6
8DISDIKBUDRp1.186.913.517.524,00Rp333.621.325.791,00Rp0,0028%9292003458Bulan 6
9KECAMATAN CINANGKARp4.923.881.531,00Rp52.894.488,00Rp0,001%191900415Bulan 3
10KECAMATAN CIKANDERp5.053.453.028,00Rp0,00Rp0,000%191900019Belum Berjalan
11BPKADRp701.102.355.756,00Rp0,00Rp0,000%424200042Belum Berjalan
12KECAMATAN BAROSRp912.000.000,00Rp0,00Rp0,000%110001Belum Berjalan
13BPBDRp17.705.792.935,00Rp8.319.974.316,00Rp0,0047%3434002311Bulan 7
14BKPSDMRp27.673.636.595,00Rp10.727.529.322,00Rp0,0039%4444003311Bulan 7
15DPRKPRp33.411.205.235,00Rp4.323.997.656,00Rp0,0013%393920307Bulan 6
16DPMDRp28.957.104.294,00Rp6.693.503.165,00Rp0,0023%3939002613Bulan 6
17DKBPPPARp32.115.137.629,00Rp10.184.935.456,00Rp0,0032%6161004021Bulan 7
18DINSOSRp15.164.544.511,00Rp3.947.593.602,00Rp0,0026%4949001138Bulan 7
19BAPENDARp59.989.984.211,00Rp29.454.138.456,00Rp0,0049%363600288Bulan 7
20KESBANGPOLRp52.652.993.200,00Rp48.696.309.798,00Rp0,0092%323200284Bulan 7
21DPMPTSPRp14.339.156.033,00Rp2.694.711.753,00Rp0,0019%3737001918Bulan 3
22DISKOPERINDAGRp16.949.365.047,00Rp6.919.041.835,00Rp0,0041%4848003513Bulan 6
23DISHUBRp43.906.498.155,00Rp17.104.371.190,00Rp0,0039%404000391Bulan 6
24DPKDRp21.386.521.679,00Rp4.992.367.616,00Rp0,0023%3939102315Bulan 7
25DPUPRRp158.632.874.013,00Rp32.880.340.866,00Rp0,0021%8080005129Bulan 6
26DISPORAPARRp14.483.382.223,00Rp7.061.548.664,00Rp0,0049%5151003219Bulan 6
27BAPPERIDARp15.358.868.217,00Rp7.700.848.839,00Rp0,0050%666600579Bulan 7
28KECAMATAN TIRTAYASARp4.429.731.000,00Rp1.965.841.689,00Rp0,0044%262610196Bulan 6
29DISNAKERTRANSRp9.745.856.404,00Rp4.549.269.165,00Rp0,0047%3838002117Bulan 7
30DISKANRp13.632.380.689,00Rp4.932.810.893,00Rp0,0036%363600324Bulan 7
31SETDARp80.964.204.138,00Rp39.360.880.159,00Rp0,0049%555500541Bulan 6
32KECAMATAN TANARARp4.141.327.512,00Rp1.228.129.044,00Rp0,0030%2121001011Bulan 6
33KECAMATAN KOPORp3.265.797.795,00Rp1.179.744.879,00Rp0,0036%773013Bulan 6
34KECAMATAN PABUARANRp4.351.960.301,00Rp1.813.197.234,00Rp0,0042%222200139Bulan 6
35KECAMATAN CIKEUSALRp3.230.227.256,00Rp1.352.673.842,00Rp0,0042%16168044Bulan 6
36KECAMATAN CARENANGRp2.983.484.794,00Rp1.484.590.371,00Rp0,0050%161600115Bulan 6
37KECAMATAN BINUANGRp3.529.468.586,00Rp1.482.334.178,00Rp0,0042%222200166Bulan 6
38KECAMATAN PULO AMPELRp3.090.690.634,00Rp1.595.365.667,00Rp0,0052%222200157Bulan 7
39KECAMATAN CIOMASRp4.045.902.632,00Rp1.861.156.268,00Rp0,0046%151500123Bulan 6
40KECAMATAN BANDUNGRp3.288.787.830,00Rp1.644.750.712,00Rp0,0050%191900136Bulan 6
41KECAMATAN TUNJUNG TEJARp3.040.875.633,00Rp1.726.649.183,00Rp0,0057%16165056Bulan 7
42KECAMATAN LEBAK WANGIRp3.606.678.242,00Rp1.482.897.428,00Rp0,0041%202000119Bulan 6
43KECAMATAN BOJONEGARARp3.411.829.666,00Rp1.708.000.578,00Rp0,0050%202000146Bulan 7
44KECAMATAN PETIRRp3.480.484.160,00Rp1.719.813.248,00Rp0,0049%191900118Bulan 6
45KECAMATAN PONTANGRp4.788.698.728,00Rp2.440.302.471,00Rp0,0051%212116023Bulan 6
46KECAMATAN CIRUASRp5.857.499.476,00Rp2.552.947.124,00Rp0,0044%18189081Bulan 6
47KECAMATAN KRAMATWATURp6.710.483.685,00Rp3.776.540.230,00Rp0,0056%232300167Bulan 7
48RSDPRp354.846.540.730,00Rp117.217.699.112,00Rp0,0033%442020Bulan 6

Kegiatan Terakhir Ditambah (BPKAD)

Total 10 hasil
#OPDNama KegiatanPagu Anggaran
1BPKADKOORDINASI DAN PENGELOLAAN PERBENDAHARAAN DAERAHRp553.590.000,00
2BPKADKOORDINASI DAN PENGELOLAAN PERBENDAHARAAN DAERAHRp678.834.000,00
3BPKADKOORDINASI DAN PENGELOLAAN PERBENDAHARAAN DAERAHRp99.225.000,00
4BPKADKOORDINASI DAN PENGELOLAAN PERBENDAHARAAN DAERAHRp634.280.347.664,00
5BPKADKOORDINASI DAN PENGELOLAAN PERBENDAHARAAN DAERAHRp9.725.750,00
6BPKADKOORDINASI DAN PENGELOLAAN PERBENDAHARAAN DAERAHRp397.211.800,00
7BPKADKOORDINASI DAN PENYUSUNAN RENCANA ANGGARAN DAERAHRp149.164.000,00
8BPKADKOORDINASI DAN PENYUSUNAN RENCANA ANGGARAN DAERAHRp152.400.000,00
9BPKADKOORDINASI DAN PENYUSUNAN RENCANA ANGGARAN DAERAHRp254.800.000,00
10BPKADKOORDINASI DAN PENYUSUNAN RENCANA ANGGARAN DAERAHRp849.106.000,00

Kegiatan Terakhir Diubah (BPKAD)

Total 10 hasil
#OPDNama KegiatanPagu Anggaran
1BPKADKOORDINASI DAN PENYUSUNAN RENCANA ANGGARAN DAERAHRp156.504.000,00
2BPKADADMINISTRASI UMUM PERANGKAT DAERAHRp11.648.460.000,00
3BPKADADMINISTRASI UMUM PERANGKAT DAERAHRp108.384.600,00
4BPKADADMINISTRASI UMUM PERANGKAT DAERAHRp90.220.800,00
5BPKADADMINISTRASI UMUM PERANGKAT DAERAHRp18.000.000,00
6BPKADADMINISTRASI UMUM PERANGKAT DAERAHRp57.728.400,00
7BPKADPERENCANAAN, PENGANGGARAN, DAN EVALUASI KINERJA PERANGKAT DAERAHRp28.878.000,00
8BPKADADMINISTRASI UMUM PERANGKAT DAERAHRp410.000.000,00
9BPKADADMINISTRASI UMUM PERANGKAT DAERAHRp167.520.000,00
10BPKADPERENCANAAN, PENGANGGARAN, DAN EVALUASI KINERJA PERANGKAT DAERAHRp14.560.000,00